CSC 492 01 Senior Design

CSC 500 01 Research Methods

 

Spring 2007

 

All Final Drafts of the presentations and reports are due Tuesdays May 11, 2004.

 

 

Home

 

 

DOWNLOADS

 

Csc492 Syllabus

Csc500 Syllabus

 

 

Senior Project Report Cover Sheet  added on 2-14-07

 

Senior project Approval Sheet added on 2-14-07

 

________________________________________________________________________________________

Progress Report Format:

          You should have your report skeleton in place

          Report Skeleton    

                   Report Cover Sheet                                     completed (refer to downloads)

                   Approval sheet                                             in progress (refer to downloads)

                   Abstract                                                      completed

                   Acknowledgement                                        in progress

                   Table of Contents                                        completed

                   Chapter one Introduction                              completed

                   Chapter two Background                              completed

                   Chapter three (your work)                            in progress

                             (May include more chapters)

                   Chapter four Conclusion/Future Work          in progress

                   References                                                   completed

                   Appendix                                                     in progress  

___________________________________________________________________

 

Submitted Senior Project Titles:

02-13-07:   Title:            Website to access the information from the Inventory Database using XML 

Student:          Eugene Chamron

            Advisor:          Richard Wasniowski

 

02-13-07:   Title:            Vehicle Awareness Device

Student:          John Nordblom

            Advisor:          Jack Han

 

02-013-07: Title:            Modern Internet Applications using Web Services 

Student:          Kenji Rudio (G)

            Advisor:          Beheshti

 

 

 

ANNOUNCEMENTS and the Semester Schedule

Monday 4/2/06

            Progress Report Presentation

                        What you have accomplished so far and what is planned for the next presentation

                        A Demo of what you have done so far

                        Report on up-to-day Findings, progress and difficulties (if any)

            Project Time Table (updated)

            using Microsoft Project Manager

            Written Progress Report _ you must have some of the subsections completed (as indicated below)   

                                                            Table of contents (completed)

                                                            Abstract (completed)

                                                            Introduction (50 - 80% Completed)

                                                            Background/Related Work (50 -80 % Completed)

                                                            The project (10 – 20 %)

                                                            Conclusion/Future work (0 -10 %)

 

            A signature from your Advisor indicating s/he is in line with you work

                   Your power point presentation must be signed by your advisor.

 

Monday 3/12/06

            Progress Report Presentation

                        What you have accomplished so far and what is planned for the next presentation

                        Report on up-to-day Findings, progress and difficulties (if any)

            Project Time Table (updated)

Using Microsoft Project Manager

            Written Progress Report _ you must have some of the subsections completed (as indicated below)        

                                                            Table of contents (completed)

                                                            Abstract (completed)

                                                            Introduction (partially done >40%)

                                                            Background/Related Work (Partially done >50%)

                                                            The project (maybe some )

                                                            Conclusion/Future work (you have time)

 

Monday 2/26/06

Project Time Table

Using Microsoft Project Manager

            Detailed Project Description

                        Software, Hardware, Functionalities, Features, etc.

            Progress Report Presentation

            Written Progress Report _ (refer to the guidelines under download)

 

Monday 2/19/06

          President’s Day

 

Monday 2/12/06

Proposal Presentations:

5-10 Minutes Power Point Presentations

            1 page written proposals with the name and signatures of Advisor and committee members                               

 

Monday 1/29/06

Self Presentations:

5-10 Minutes Power Point Presentations

            Hard copy of the presentation

                                   

Monday 1/22/06

First Class